Hi Folks, As we close in on the end of week 1 - the volume of testing I can see evident in the interop system is concerning. Given we have a range of new test cases and profiles in the mix, there is a reasonable chance that Participants will need to make adjustments and if we leave all of the reporting until next week, it undermines reason we stretch this over 2 weeks. Could I ask all Client Operators to push on with at least a first round of testing and upload the results into the Interop System so the Server Operators can check the status. Ideally, I'd like to see all results completed by the end of this week so as a group we can focus on the failures and make some determinations in time for Participants to amend their implementations and retest. For reference, I can see 10 results out of the possible 57,576. This equates to .0002% completion. Please, if you have any questions or concerns, let me know directly or post to the list. Thanks again, -Tony