Please find below a DRAFT TC timeline for your review. Let’s discuss and refine this, leading up to and during the F2F meeting Nov 8 and 9, 2012. The purpose of this timeline exercise is to create a map of the future milestones (based on current knowledge) and lay out a probable path for traversing the various future milestones. As with all things, there are unknowns that may stretch the timeline. For example, what if there are many public comments? What if it takes more time for the TC to address existing and as yet unknown issues? Those unknowns may stretch the timeline in terms of having to produce multiple Committee Specification Drafts until we address all the issues and feel confident to advance the Work Products to Committee Specification. Thanks. --- DRAFT TC timeline --- Goal: Deliver core Work Products as close as possible to the timeline mentioned in the TC charter and extension Work Products soon after. Draft timeline for core Work Products: November 2012 2 nd F2F meeting Nov 8-9, 2012 (Littleton, MA) Discuss new proposals Aim to resolve many of the key issues on core Work Products such as enums and relationship simplification Leading up to Nov 29 Editors to incorporate all issue resolutions and produce new revisions of core Work Products Review and file issues on core Work Products resulting from new proposals Review and file issues on core Work Products resulting from extension Work Products Nov 15 th TC meeting [Cancelled? – since it is the week after the F2F] Nov 22 nd TC meeting [Cancelled? – since it is the Thanksgiving holidays in the US] Nov 29 TC meeting Continue to make progress on issues December 2012 Continue to make progress on issues December 19, 2012 * File all known issues on core Work Products resulting from new proposals * January 2013 January 17, 2012 * File all known issues on core Work Products resulting from extension Work Products * Continue to resolve issues 3 rd F2F meeting January 29-31, 2013 (tentative) (details TBD) Resolve all key issues on core Work Products * TC agrees to a high bar for accepting new issues on core Work Products * Continue to resolve issues February 2013 February 7, 2013 Resolve * all remaining issues * on Core Work Products Agree to advance core Work Products to Committee Specification Draft 01 (CSD01) February 14, 2013 Editors to prepare Committee Specification Draft 01 (CSD01) of core Work Products containing resolutions to all issues February 21, 2013 Approve Committee Specification Draft 01 (CSD01) of core Work Products and agree to start 30-day public review March 2013 March 1 through March 30 30-day public review of core Work Products Address public review comments on core Work Products April 2013 4 th F2F meeting (April 2-4, 2013) Address public review comments on core Work Products NOTE: If there are no public review comments, we can jump ahead to * approving Committee Specification (CS) * April 18, 2013 Address all public review comments on core Work Products Agree to advance core Work Products to Committee Specification Draft 02 (CSD02) Leading up to April 25, 2013 Editors to prepare Committee Specification Draft 02 (CSD02) of core Work Products containing resolutions to all issues April 25, 2013 Approve Committee Specification Draft 02 (CSD02) of core Work Products and agree to start 15-day public review May 2013 May 1 through 15, 2013 15-day public review May 23 Assuming there are no changes to core Work Products resulting from the preceding public review, * approve Committee Specification (CS) * NOTE: If there are substantive changes to the core Work Products resulting from the preceding public review, then we will need to extend the timeline and produce CSD03 and so on. Early June 2013 Approve Candidate OASIS Standard (COS) Mid-June and mid-August 2013 60-day public review August 2013 OASIS Standard (OS) Draft timeline for extension Work Products: · November 29, 2012 Review and file issues on core Work Products resulting from extension Work Products January 17, 2013 * File all known issues on core Work Products resulting from extension Work Products * February and March 2013 Resolve issues on extension Work Products April 2-4, 2013 4 th TC F2F meeting Resolve issues and make progress on extension Work Products · May 2013 o Approve Committee Specification Draft 01 of extension Work Products (depending on progress)