OASIS ebXML Messaging Services TC

  • 1.  Re: [ebxml-msg] Schedule

    Posted 12-20-2006 06:00
    Here is a draft schedule for discussion since 
    I saw nobody volunteering to draft it.
    
    --
    About one month+ for resolving all issues, comments, and editorial
    updates. It is by the first week of February 2007.
    
    One week for the final TC review, one (to two) week(s) to incorporate
    the comments. The following two voting is on the third week or 4th week
    of February.
        1) making the spec Committee Draft.
        2) deciding whether there is substantial change in the new CD or not.
             OASIS rule requires a second 15days public review, if the
             spec has substantial change.
    
    If we need 15days second public review, we will submit it for a second
    public review by the end of February. 
    Then the target date for OASIS submission is April 15, 2007.
    
    If we do not need second public review, we will submit it to OASIS for
    final member voting by March 15, 2007. In this case, we need the
    following additional two voting. Note these are super majority vote.
        3) making the CD to Committee Specification.
        4) submitting the CS to OASIS member voting.
    
    Thoughts?
    
    Thanks,
    
    Iwasa