Re: Kris - Don: Request to Review Stage 3 Troubleshooting Proposals 13086, 13096, and 13098

  • 1.  Re: Kris - Don: Request to Review Stage 3 Troubleshooting Proposals 13086, 13096, and 13098

    Posted 06-11-2013 00:20
    Hi, Stan. I'll add them to the agenda. I assume that you are looking for reviewers since the earlier packages weren't complete? Best, Kris Kristen James Eberlein Principal consultant, Eberlein Consulting Co-chair, OASIS DITA Technical Committee Charter member, OASIS DITA Adoption Committee www.eberleinconsulting.com +1 919 682-2290; kriseberlein (skype) On 6/10/2013 8:14 PM, Stan Doherty wrote: Hi --   At the TechComm SC meeting earlier today, the SC reviewed outstanding updates to the three Stage 3 proposals for troubleshooting elements. Bob has uploaded the supporting files to the OASIS repository. Great job Bob!! 13086, step troubleshooting, is in phase 3 (Add troubleshooting element to a step) 13096, task troubleshooting, is in phase 3 (Add troubleshooting section with a task) 13098, note type-attribute value trouble, is in phase 3 (Add trouble admonition (note type)) https://www.oasis-open.org/committees/document.php?document_id=49486&wg_abbrev=dita-techcomm At the earliest opportunity, we'd love to have these Stage 3 proposals reviewed by the TC.   Is there any chance that we could get on the TC agenda for tomorrow (06/11/2013)??   Many thanks --   Stan   P.S. I have updated Trello for these items.


  • 2.  Re: [dita-techcomm] Re: Kris - Don: Request to Review Stage 3 Troubleshooting Proposals 13086, 13096, and 13098

    Posted 06-11-2013 01:17
    Kris, These have already been reviewed. Are we reviewing everyone twice?  JoAnn Sent from my iPad JoAnn Hackos Comtech Services Inc 710 Kipling Street Suite 400 Lakewood CO 80215 On Jun 10, 2013, at 6:20 PM, "Kristen James Eberlein" < kris@eberleinconsulting.com > wrote: Hi, Stan. I'll add them to the agenda. I assume that you are looking for reviewers since the earlier packages weren't complete? Best, Kris Kristen James Eberlein Principal consultant, Eberlein Consulting Co-chair, OASIS DITA Technical Committee Charter member, OASIS DITA Adoption Committee www.eberleinconsulting.com +1 919 682-2290; kriseberlein (skype) On 6/10/2013 8:14 PM, Stan Doherty wrote: Hi --   At the TechComm SC meeting earlier today, the SC reviewed outstanding updates to the three Stage 3 proposals for troubleshooting elements. Bob has uploaded the supporting files to the OASIS repository. Great job Bob!! 13086, step troubleshooting, is in phase 3 (Add troubleshooting element to a step) 13096, task troubleshooting, is in phase 3 (Add troubleshooting section with a task) 13098, note type-attribute value trouble, is in phase 3 (Add trouble admonition (note type)) https://www.oasis-open.org/committees/document.php?document_id=49486&wg_abbrev=dita-techcomm At the earliest opportunity, we'd love to have these Stage 3 proposals reviewed by the TC.   Is there any chance that we could get on the TC agenda for tomorrow (06/11/2013)??   Many thanks --   Stan   P.S. I have updated Trello for these items.


  • 3.  Re: [dita-techcomm] Re: Kris - Don: Request to Review Stage 3 Troubleshooting Proposals 13086, 13096, and 13098

    Posted 06-11-2013 13:33
    Hi, JoAnn. The idea behind the stage 3 review is that TC members look at a whole, complete proposal. Part of their job is to ensure that the proposal include everything it needs, also to review new topics and changes to existing topics before the TC takes a look at them. Happy reviewers then stand with the proposal owner as champions during the TC discussion and vote I assumed you were looking for a 2nd review for the following reasons: The subcommittee has added new content (albeit small) to the proposal since it was first reviewed. The package in Kavi only includes source files. If the subcommittee wants to move this directly to the stage 3 discussion phase, please upload the following to Kavi and send an e-mail to the list: A built version of the proposal. This can be a single HTML file or PDF or CHM or whatever. A zip of DITA source that is in sync with the built proposal Best, Kris Kristen James Eberlein Principal consultant, Eberlein Consulting Co-chair, OASIS DITA Technical Committee Charter member, OASIS DITA Adoption Committee www.eberleinconsulting.com +1 919 682-2290; kriseberlein (skype) On 6/10/2013 9:16 PM, JoAnn Hackos wrote: Kris, These have already been reviewed. Are we reviewing everyone twice?  JoAnn Sent from my iPad JoAnn Hackos Comtech Services Inc 710 Kipling Street Suite 400 Lakewood CO 80215 On Jun 10, 2013, at 6:20 PM, Kristen James Eberlein < kris@eberleinconsulting.com > wrote: Hi, Stan. I'll add them to the agenda. I assume that you are looking for reviewers since the earlier packages weren't complete? Best, Kris Kristen James Eberlein Principal consultant, Eberlein Consulting Co-chair, OASIS DITA Technical Committee Charter member, OASIS DITA Adoption Committee www.eberleinconsulting.com +1 919 682-2290; kriseberlein (skype) On 6/10/2013 8:14 PM, Stan Doherty wrote: Hi --   At the TechComm SC meeting earlier today, the SC reviewed outstanding updates to the three Stage 3 proposals for troubleshooting elements. Bob has uploaded the supporting files to the OASIS repository. Great job Bob!! 13086, step troubleshooting, is in phase 3 (Add troubleshooting element to a step) 13096, task troubleshooting, is in phase 3 (Add troubleshooting section with a task) 13098, note type-attribute value trouble, is in phase 3 (Add trouble admonition (note type)) https://www.oasis-open.org/committees/document.php?document_id=49486&wg_abbrev=dita-techcomm At the earliest opportunity, we'd love to have these Stage 3 proposals reviewed by the TC.   Is there any chance that we could get on the TC agenda for tomorrow (06/11/2013)??   Many thanks --   Stan   P.S. I have updated Trello for these items.